This Will Only Take Twenty Minutes
The planning fallacy and why our schedules forget ordinary life
You can work hard all afternoon and still feel behind if the afternoon was planned for a person who never gets interrupted. Understanding the planning fallacy can help you make commitments that fit the life you actually have.

The short answer
The planning fallacy is the tendency to expect a task to finish sooner than it does, even when similar tasks have taken longer before. A useful response is to compare your plan with real experience, include the less visible work, and leave room for uncertainty. The aim is a more credible estimate, not a perfectly controlled day.
The quick task that borrowed your evening
You have twenty minutes before dinner. Plenty of time to send that email.
Except the email needs an attachment. The attachment needs one small correction. The correction sends you looking for a figure in another document. Then you discover that the file called FINAL is not quite as final as its name suggests.
Forty-five minutes later, dinner is cooling and you are annoyed with yourself. How did such a small job take so long?
Perhaps you were distracted. Perhaps the task changed. But consider another possibility: your original estimate described only the most visible part of the work. You imagined pressing send. You did not give the preparation, checking and minor complications anywhere to live.
That gap between an appealing plan and an ordinary day is where the planning fallacy becomes recognisable.
What the research actually found
In a 1994 study, Roger Buehler, Dale Griffin and Michael Ross asked psychology students when they expected to finish their honours theses. Among the 33 students with recorded completion dates, the average best estimate was 33.9 days. Actual completion averaged 55.5 days. Four additional students had not finished when tracking ended and were excluded from those averages.
This was a small student sample, not a rule for every person or project. Nevertheless, the discrepancy illustrates something familiar: knowing that work often runs late does not necessarily make our next estimate realistic.
Why a convincing plan can still be misleading
Imagine planning to assemble a bookcase. The mental version is beautifully efficient: open the box, follow the instructions, stand it upright. The real version may also include finding the screwdriver, clearing the floor, and discovering that you attached one panel backwards.
In two experiments published in 2003, Buehler and Griffin found that prompting people to generate concrete, detailed plans for future tasks made their completion predictions more optimistic without producing corresponding improvements in actual completion times. The tasks involved Christmas shopping and major academic assignments.
This does not mean planning is harmful. It means that imagining a coherent sequence is not the same as checking whether the estimate is credible. A plan can explain how you hope to proceed while leaving out the circumstances in which you will be doing it.
Your future self may know exactly what to do. They will still need to eat lunch.

Working time and finishing time are different questions
A report might require two hours of focused work. That does not mean it will be ready two hours from now. You may need a colleague’s figures, a quiet period to concentrate, and time to check the finished version.
Researchers distinguish performance time, the time spent working on the task itself, from completion time, when it is actually finished. Interruptions, competing activities and waiting can separate the two.
Before promising a delivery time, ask both questions: How much work is involved? When can that work realistically happen?
A small task can contain several hidden jobs
“Cook dinner” can include choosing a meal, checking ingredients, shopping, preparing food and washing up. A recipe’s cooking time may describe only one part of that sequence.
In experiments by Justin Kruger and Matt Evans, people prompted to break tasks into components generally gave longer estimates; in two experiments that measured actual duration, those estimates were less biased.
However, a longer list is not automatically a better forecast. Later experiments found that estimates could increase, decrease or remain unchanged depending on which components people considered. A checklist dominated by easy steps can still leave the difficult part out.
The practical question is not “Have I made a detailed list?” It is “Have I included what usually takes the time?”
When a missed estimate becomes a judgement about you
There is an emotional layer to this. If you expect to complete six things and manage three, you may describe the day as a failure without examining whether six was ever feasible.
For reflection, separate three statements: “The task took longer than I expected.” “I need to change how I plan it.” “I am unreliable.” The first describes an event. The second suggests an action. The third turns that event into a broad judgement about your identity.
Taking responsibility remains important, especially when others depend on you. You can apologise for a missed commitment, communicate earlier next time, and improve the estimate without treating every delay as a character flaw.
Try a small reality check before your next promise
Choose one recurring task rather than reorganising your whole life. The following exercise adapts ideas from the research into everyday questions; it is not a validated assessment.
1 Define what finished means
Does “finish the presentation” mean a rough draft, checked slides, or slides plus rehearsal? Write the endpoint before estimating. Otherwise, the amount of work can expand while the original promise stays fixed.
2 Check comparable occasions
Look at how long similar work actually took, using records where available. In one experiment, explicitly connecting relevant experience to a new prediction removed the average optimistic bias in that task. Treat previous attempts as useful evidence, while allowing for genuine differences.
3 Count the less visible work
Include setup, searching, checking, communication and cleanup where they apply. Ask what must happen before you can begin and whose input you need. A task list should show the work around the work.
4 Allow for uncertainty and make the tradeoff visible
An estimate can be a range: “About 40 to 60 minutes, depending on whether the information is ready.” There is no universally correct percentage of extra time. Use your own pattern of variation and consider the consequences of being late. If the work will not fit, decide what can move or become smaller.
5 Compare afterwards without turning it into a trial
Record the estimate, the actual time and one reason for any difference. Was a step missing? Did the scope change? Were you waiting for someone? Use that information for the next attempt instead of simply promising to try harder.
An ordinary example
Suppose Alex estimates twenty minutes to prepare a short update. The last three similar updates actually took 30, 40 and 35 minutes. Together that is 105 minutes; divided by three, the average is 35 minutes. Twenty minutes now looks like an optimistic starting point.
Alex might reserve 45 minutes this time because the update needs an extra check. Those ten additional minutes are a judgement about this particular task, not a scientific formula. If only twenty minutes are available, Alex can prepare the outline now and schedule the remaining work, or agree a smaller deliverable.
This is an illustrative example. Its purpose is to make the choice visible before the deadline arrives.

Another way to see the missing steps
Try starting at the finish and working backwards: before the report is sent, it needs checking; before checking, a complete draft; before drafting, the missing figures. In four experiments, backward planning produced later predictions; in the final experiment, which tracked real completion, it reduced optimistic bias without making people finish sooner.
Use it as another view of the work, then check the result against experience. It cannot create time or remove a dependency.
Some schedules need fewer demands
An overloaded employee cannot solve understaffing with a better notebook. A parent caring for a sick child may have little control over interruptions. Sometimes the honest conclusion is that the workload, deadline or support needs to change.
Likewise, a late finish alone cannot tell us why someone struggled. Scope changes, missing resources and unexpected events deserve consideration before we reach for a psychological label.
A useful conversation might begin: “I can complete this carefully by Thursday. If it must be Wednesday, which part should we simplify or postpone?” That makes the constraint available for discussion.
Make room for the person who will do the work
You do not need to abandon ambition. You can let your plans include preparation, waiting, recovery and an occasional wrong turn.
Before saying “This will only take twenty minutes,” pause long enough to ask what those twenty minutes contain. A realistic estimate gives you and the people relying on you something useful: a chance to choose before the day is already over.
A plan becomes kinder when the real person doing the work is allowed to appear in it.
A question to take with you
Which task do you repeatedly underestimate, and what part of it disappears when you imagine getting it done?
Glossary
Planning fallacy. Expecting a task to finish sooner than it does despite relevant experience of previous delays.
Outside view. Using comparable past outcomes to inform a forecast, alongside the details of the current task.
Task unpacking. Breaking a broad activity into components so that its requirements are easier to examine.
Completion time. When the task is finished, including the effects of waiting and competing demands.
Evidence and further reading
Numbered citations in the article refer to the original studies below. Findings concern particular tasks and samples; the practical exercise is an editorial adaptation rather than a tested programme.
[1] Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the planning fallacy: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366–381.
[2] Buehler, R., & Griffin, D. (2003). Planning, personality, and prediction: The role of future focus in optimistic time predictions. Organizational Behavior and Human Decision Processes, 92(1–2), 80–90.
[3] Kruger, J., & Evans, M. (2004). If you don’t want to be late, enumerate: Unpacking reduces the planning fallacy. Journal of Experimental Social Psychology, 40(5), 586–598.
[4] Hadjichristidis, C., Summers, B., & Thomas, K. (2014). Unpacking estimates of task duration: The role of typicality and temporality. Journal of Experimental Social Psychology, 51, 45–50.
[5] Wiese, J., Buehler, R., & Griffin, D. (2016). Backward planning: Effects of planning direction on predictions of task completion time. Judgment and Decision Making, 11(2), 147–167.